Maintaining electric infrastructure in the Tahoe region can present challenges that don't exist in many other places. Steep slopes, rugged terrain, and limited road access can make inspecting and repairing power lines especially difficult. Sometimes, keeping the power flowing safely and reliably means taking to the air.

That was the case recently when Liberty crews completed maintenance work on the 111-transmission line, one of the main lines that delivers power from Nevada to our customers in the South Lake Tahoe area.

Many of the issues repaired during the project were first identified through Liberty's new drone inspection program. Using drones, our team can closely inspect poles, power lines, and other electrical equipment in areas where traditional, ground-based inspections can be difficult. For South Lake Tahoe, a high fire threat area, this program helps to proactively identify conditions that could lead to increased wildfire risk or reliability issues.

Once the inspection findings were reviewed and the necessary repairs identified, crews faced the next challenge: reaching equipment located in some of Tahoe's most difficult terrain. To address this issue, a much larger aircraft was needed. Helicopters helped our crews access remote locations that conventional vehicles and equipment would have difficulty reaching so they could complete repairs.

Working safely and efficiently in these conditions requires considerable coordination. Crews must account for rugged terrain, specialized equipment, helicopter operations, and the normal complexities of working around energized electric infrastructure.

The project also illustrates the value of pairing new inspection technology with the experience of our field employees. The drone inspections played an essential role in providing a detailed view of infrastructure and helping to identify potential concerns, while our experienced lineworkers and other specialists determined what needed to be repaired and how to safely accomplish the work.

Overall, the 111 Line project demonstrates the range of people, technology, and planning involved in maintaining our electric system. In total, thirty-seven Liberty employees and contractors were on the job site, and six structures were replaced in a single day.

Most customers will never see this kind of work firsthand. But every inspection completed and every repair made contributes to the same goal: maintaining a safer, stronger, and more reliable electric system for the customers and communities we serve.